Location: Námestovo
Construction commencement: September 2017
Construction completion: October 2017
Construction type: Petrol stations
Activity: Project management
Investor: SLOVNAFT, a.s.
Construction: Námestovo fuel station
Construction type: fuel stations
Activity: Project management
Investor: SLOVNAFT, a.s.
Project manager: Ing. Tomáš Krutek
Scope of work at the station in Námestovo:
Complete layout adjustment, including the background, change of ceramic cladding, paving and the equipment, painting of the space, change of RVI elements, lighting, and furniture