Construction: TTIP PO 01 administrative building reconstruction – Trnava Industrial Park II, production and installation of an information pylon and the Mikovíniho street TTIP entrance adjustment
Location: Trnava, Priemyselná street
Construction commencement: 06/2019
Construction completion: 11/2019
Construction type: administrative building, pylon
Activity: General contractor
Investor: the city Trnava
Project manager: Ing. Ivan Králik
Scope of work:
reconstruction of the PO 01 administrative building in TTIP – Trnava Industrial Park II, change of floors, electricity, central heating system reconstruction, installation of a new ventilation, the production and installation of a new pylon and an adjustment of the TTIP entrance in Mikovíniho street.