Construction: GS Slovnaft – Žilina, Šibenice – correction of the handling area
Activity: Realization
Project manager: Ing. Tomáš Krutek
Start of the construction: may 2016
End of the constructiom: may 2016
Locality: Slovnaft a.s., GS Slovnaft Košická II, street Košická, 010 01 Žilina.
Betónová plocha na čerpacej stanici bola čiastočne v nevyhovujúcom technickom stave. Pri výdajných stojanoch sa prejavilo značné znehodnotenie a poškodenie konštrukčných vrstiev. Stavebné práce sa rozdelili na 2 etapy:
The concrete surface at the gas station was partially in a noncomforming condition. Fuel dispensers were signifcantly damaged and construction layers were destroyed. Construction works were divided into 2 stages:
- 1. stage: complete reconstruction of the concerete layers between fuel dispensers 6 and 7,
- 2. stage: correction of forfeited asphalt surface in front of the fuel dispensers.